Prior to any physical handling, our engineering team conducted a thorough review of cargo specifications. This included detailed analysis of weight distribution patterns, dimensional profiles, and center of gravity calculations for each farm tank and stair tower module.
The technical assessment informed the development of customized lifting plans, identifying optimal sling angles, spreader bar requirements, and crane positioning for each unit. Special attention was given to the 100.526-ton farm tank, which required a multi-point lifting arrangement to ensure even load distribution and prevent structural stress.
Our planning process also encompassed risk assessment protocols, identifying potential hazards and establishing mitigation measures. Weather windows, tidal conditions, and vessel stability factors were integrated into the operational timeline.