DEE Delight Handles 90-Metre Wind Turbine Blades and 100-Ton Drive Trains for Wind Farm Project

Table of Contents

Rotor blades exceeding 90 metres, a 53-ton hub, a 40-ton nacelle and drive trains approaching 100 tons each — handled at C-0 terminal Laemchabang port under manufacturer lifting standards.

Wind turbine blades in blue transport cradles being handled by DEE Delight at Chuk Samet Port, Thailand
Wind turbine rotor blades in engineered transport cradles during handling operations at C-0 terminal Laemchabang port.

LAEMCHABANG PORT, THAILAND — August 2, 2026 — DEE Delight Port Stevedoring Services has completed a wind turbine generator component handling operation at C-0 terminal Laemchabang port, covering rotor blades exceeding 90 metres in length and drive train units approaching 100 tons each, in support of a wind farm project.

The operation extends the company’s heavy-lift and project-cargo capability into the clean energy sector, and follows its handling of an 800-ton Super Heavy Module at the same port earlier in 2026.

Every component was handled under the lifting and handling standards specified by the turbine manufacturer, with engineering planning, risk assessment and operational control applied at each stage of the sequence.

Wind Turbine Components Handled at C-0 terminal Laemchabang port

The scope covered the four principal assemblies of a wind turbine generator. Each carries a different combination of mass, dimension and handling restriction.

Component Specification Primary handling constraint
Rotor blade Over 90 metres long, approx. 37 tons each Wind-load sensitivity; risk of bending or twisting along the span
Hub Approx. 53 tons Concentrated mass with restricted lifting-point geometry
Nacelle Approx. 40 tons Enclosed assembly; orientation and shock-load limits
Drive train Approx. 100 tons each Lifting-point design, load distribution and centre-of-gravity control

Taken together, the components sit well outside standard container and breakbulk handling: extreme length in the blades, extreme concentrated mass in the drive trains, and precision orientation requirements across all four.

Why Wind Turbine Components Are Classified as Out-of-Gauge Cargo

Mr. Krit Seetongoon, Chief Executive Officer of DEE Delight Port Stevedoring Services, said the component set falls into two of the most demanding categories in cargo handling.

“Wind turbine component handling falls under Project Cargo and Out of Gauge (OOG) Cargo. Each component carries its own constraints — dimensions, weight, centre of gravity and permitted lifting method. There is no single standard procedure that covers all of them,” he said.

Out-of-gauge cargo exceeds the dimensional limits of standard transport and handling equipment. In practice that means no single lifting arrangement covers the full component set: each assembly requires its own rigging design, equipment selection and handling sequence.

Rows of wind turbine rotor blades secured in blue steel cradles on the quay at Chuk Samet Port
Rotor blades staged in engineered cradles. Each blade exceeds 90 metres and weighs approximately 37 tons.

The Engineering and Logistics Planning Sequence

Before any component was lifted, the DEE Delight project team worked through a four-stage planning sequence:

  1. Component study — establishing the physical characteristics of each assembly, including dimensions, mass, centre of gravity and manufacturer-designated lifting points.
  2. Risk analysis — assessing operational risk across weather exposure, equipment capacity, quay conditions and personnel positioning.
  3. Lifting method design and equipment selection — specifying the rigging arrangement and lifting gear appropriate to each component.
  4. Operational sequencing — ordering the on-site steps so each lift is executed in a controlled, repeatable sequence.

The objective across all four stages is consistent: deliver the cargo safely, on schedule, and in the condition the manufacturer requires.

Handling 90-Metre Blades in Open Wind Conditions

At over 90 metres, the rotor blades were the longest components in the scope and the most sensitive to environmental conditions. A blade of that length presents a large surface area to crosswind, and the resulting load can induce bending or twisting along the span during lifting and translation.

The handling arrangement addressed this through engineered blade cradles that support the aerofoil at designated contact points, controlled lift speeds, and tag-line management to limit rotation. Wind conditions were monitored throughout, with defined limits governing whether a lift could proceed.

DEE Delight rigging crew handling a wind turbine blade section alongside a project cargo vessel at Chuk Samet Port
A blade section rigged for transfer alongside the vessel. Rigging arrangement and lift speed are designed per component.

Load Distribution and Vessel Stability for 100-Ton Drive Trains

The drive train units presented the opposite engineering problem: concentrated mass rather than extended length.

At close to 100 tons each, lifting-point selection and load distribution had to be designed rather than assumed. The team evaluated the centre of gravity of each unit, verified that the rigging arrangement held the load level through the full lift arc, and coordinated with the vessel to maintain trim and stability as weight was transferred.

Building on the 800-Ton Super Heavy Module Operation

The wind turbine scope draws directly on the company’s earlier work at C-0 terminal Laemchabang port, where DEE Delight engineered and executed the handling of a Prefabricated Unit weighing 837,593 kilograms and measuring approximately 43 metres long, 14 metres wide and 12 metres tall, bound for Baytown, Texas.

That operation established the engineering discipline the company now applies across sectors: rigging design, multi-party coordination and site control at a scale handled routinely by few operators in Thailand. Read the full 800-ton Super Heavy Module operation report.

DEE Delight project cargo team in branded safety vests supervising a wind turbine blade lift at Chuk Samet Port
DEE Delight personnel supervising component transfer. Site control and safety supervision run for the full operational sequence.

Thailand’s Clean Energy Build-Out and Project Cargo Demand

Investment in clean energy, infrastructure and heavy industry across Thailand is creating sustained demand for heavy-lift and project-cargo capability. Wind in particular moves cargo profiles through Thai ports that did not exist at volume a decade ago.

Krit said the company’s objective extends beyond individual operations.

“Our goal is to raise the capability of Thai personnel alongside engineering and safety standards. That is what allows us to support large domestic projects and improve the competitiveness of Thai operators at a regional level,” he said.

Project cargo vessel loaded with tiers of wind turbine blades in transport frames at Chuk Samet Port, Thailand
Wind turbine blades stowed in tiered transport frames aboard the project cargo vessel.

Frequently Asked Questions

What cargo category do wind turbine components fall under?

Wind turbine components are handled as Project Cargo and Out of Gauge (OOG) Cargo. OOG cargo exceeds the dimensional limits of standard transport and handling equipment, so each component requires a purpose-designed rigging arrangement rather than a standard lifting procedure.

How are 90-metre wind turbine blades handled at port?

Blades of this length are supported in engineered cradles that contact the aerofoil at designated points, preventing bending or twisting along the span. Lifts are executed at controlled speed with tag-line management to limit rotation, and wind conditions are monitored against defined operating limits throughout.

What is the heaviest component in a wind turbine generator set?

In this scope the drive train was the heaviest single component at approximately 100 tons per unit, followed by the hub at approximately 53 tons and the nacelle at approximately 40 tons. Rotor blades are the longest at over 90 metres but comparatively light at approximately 37 tons each.

What is the difference between heavy lift and project cargo?

Heavy lift refers to cargo that exceeds the capacity of standard lifting equipment and requires specialist cranes and rigging. Project cargo is the broader category covering oversized, high-value or complex consignments that require integrated engineering, planning and multi-party coordination — often including heavy lift as one element.